请教BAAN LN 中有关 lead time 方面的一个小问题

[复制链接]
发表于 2008/11/12 15:33:23 | 显示全部楼层 |阅读模式

马上注册,结交更多好友,享用更多功能,让你轻松玩转社区。如果您注册时有任何问题请联系客服QQ: 83569622  。

您需要 登录 才可以下载或查看,没有帐号?注册

x
lead time教程中有一个 start of fixed lead-time Horizon(SFC),不知道什么意思和用途?请教高手,谢谢!!
 楼主| 发表于 2008/11/13 11:33:37 | 显示全部楼层
还有 EP offset 是啥意思?Horizon在 Baan 中代表什么专业的意思呢?
 楼主| 发表于 2008/11/24 14:44:50 | 显示全部楼层
Fixed lead-time horizons
In addition to the lead-time components, you must define a horizon. In ERP
LN, a horizon indicates a time period. In the period before the start date of
the horizon, short-term, detailed planning of lead times is applied, using
several lead-time components on the basis of routing data.

Terms and definitions
Term Definition
EP-offset: Time between the requirement date and the planned
order finish date. This consists of outbound lead time,
extra lead time, safety time. For purchase orders also
inbound and item supplier safety time

自问自答,horizon就是一个时间段,offset就是结束日期和需求日期之间的时间段,其时间长短由一系列lead time来控制。

怪自己没仔细研究教程,呵呵,不过这个版块的人气也是。。。。
 楼主| 发表于 2008/11/25 15:15:04 | 显示全部楼层
哈哈,通俗易懂,非常感谢Andy兄!!

不过这里:“超过这个时间段的用订单的提前期,在这个之内的用ROU中按订单量计算的提前期. 如果你设的是60天.则60天以后的订单不管数量,全设为提前10天.而60天以内的,是按数量来计算的. 订单量10的话,就是提前10小时.”

应该是“60天以后的订单不管数量,全设为提前60天”吧?
 楼主| 发表于 2008/11/25 21:27:20 | 显示全部楼层
啊,开始没看仔细呵呵。
也就是说:固定提前期为60天。60天外的,用生产提前期(10天)来计算,60天内的,用ROU时间×物料数量来计算。
谢谢Andy兄~
发表于 2009/2/17 11:21:43 | 显示全部楼层
OK.very good
您需要登录后才可以回帖 登录 | 注册

本版积分规则

QQ|Archiver|小黑屋|手机版|壹佰网 ERP100 ( 京ICP备19053597号-2 )

Copyright © 2005-2012 北京海之大网络技术有限责任公司 服务器托管由互联互通
手机:13911575376
网站技术点击发送消息给对方83569622   广告&合作 点击发送消息给对方27675401   点击发送消息给对方634043306   咨询及人才点击发送消息给对方138011526

GMT+8, 2025/11/29 03:44 , Processed in 0.012968 second(s), 14 queries , File On.

Powered by Discuz! X3.4

Copyright © 2001-2020, Tencent Cloud.

快速回复 返回顶部 返回列表